
Project Conducted Under Employers

All below mentioned project's Quantity Surveying part was conducted by QS4U crew on behalf of an employer organization or an individual employer. With the quality of service, the transparency of work & presenting skill always lead our client's to recommend QS4U from one project to another.
Services That We Are Offering On Behalf Of Employers
Cost Administration, Cost Consultancy, Cost Managements, Bill Valuations, Project Estimates, Independent Valuations, Value Engineering,...
Cost Administration, Cost Consultancy, Cost Managements, Bill Valuations, Project Estimates, Independent Valuations, Value Engineering,... easy.

OUR TEAM
I'm a paragraph. Click here to add your own text and edit me. It’s easy. Just click “Edit Text” or double click me to add your own content and make changes to the font.
Read More


200Mn Individual Residence at Pamankada
Project Nature: Individual residence with 2 Lifts, 02 Steal stairs, 02 kumbuk stairs, Marble flooring in general areas, special timber
flooring in master bedrooms, special heat resistant roof terrace and massive decorative external steel structure including 04 master bedrooms, 12 normal bedrooms and 16 bathrooms
Status: Completed (Defect liability period is going on)
Completed: 2022
Contract Amount: 200Mn
QS4U Involvement: Design was changed from 47Mn to 200Mn while construction is going on and 600+ variations were occurred. As a professionals Qs4U was the only QS in this project involved with Main contractor's payment application preparation and certifying after convincing the client
![]() | ![]() | ![]() | ![]() |
---|---|---|---|
![]() | ![]() |


Individual Residence at Malabe
-
Status: Completed (Defect liability period is going on)
-
Completed: 2022
-
Contract Amount: 80Mn
-
Project Nature: Individual residence & lump sum project.
-
QS4U Involvement: Construction was started in early 2020 and COVID lockdowns were affected to the project progress. Economic crisis was also affected to this lump sum project. Both parties mutually agreed to end the Contract agreement and QS4U implemented a new tool and both parties agreed to continue the project using stage wise quotations. Commencement of each stage material advance was to be paid and QS4U had to always make sure the client's money assurance since there wasn't any advance guarantee & the project cashflow.
Individual Residence at Nawala
-
Status: Completed (Defect liability period is going on)
-
Completed: 2022
-
Contract Amount: 20Mn
-
Project Nature: Individual residence & lump sum project.
-
QS4U Involvement: Construction was started in early 2019 and COVID lockdowns were affected to the project progress. Economic crisis was also affected to this lump sum project.
Individual Residence at Pepiliyana
-
Status: Completed (Defect liability period is going on)
-
Completed: 2018
-
Contract Amount: 20Mn
-
Project Nature: Individual residence & constructed by various labour contractors
-
QS4U Involvement: Construction was started in early 2020 and COVID lockdowns were affected to the project progress. Economic crisis was also affected to this lump sum project. Both parties mutually agreed to end the Contract agreement and QS4U implemented a new tool and both parties agreed to continue the project using stage wise quotations. Commencement of each stage material advance was to be paid and QS4U had to always make sure the client's money assurance since there wasn't any advance guarantee & the project cashflow.

Villa & Chalets at Ella
Construction was started in early 2019 and COVID lockdowns were affected to the project progress. Economic crisis was also affected to this lump sum project.
-
Status: Phase 01 Completed
-
Completed: 2022
-
Contract Amount: 05Mn
-
Project Nature: Constructed by various labour contractors.
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() | ![]() |