QS4U, A Professional Quantity Surveying firm which is operating under a registered company with private liability. As a professional individual freelancing agency, QS4U has operated with some remarkable projects after being recommended by industry professionals such as project managers, Adjudicators, Arbitrators and CGF (Construction Guaranteed Fund - CIDA).
Project conducted under Employers
All below mentioned project's Quantity Surveying part was conducted by QS4U crew on behalf of an employer organization or an individual employer. With the quality of service, the transparency of work & presenting skill always lead our client's to recommend QS4U from one project to another.
Title: 200Mn Individual Residence at Pamankada
Status: Completed (Defect liability period is going on)
Completed: 2022
Contract Amount: 200Mn
Project Nature: Individual residence with 2 Lifts, 02 Steal stairs, 02 kumbuk stairs, Marble flooring in general areas, special timber
flooring in master bedrooms, special heat resistant roof terrace and massive decorative external steel structure including 04 master bedrooms, 12 normal bedrooms and 16 bathrooms.
QS4U Involvement: Design was changed from 47Mn to 200Mn while construction is going on and 600+ variations were occurred. As a professionals Qs4U was the only QS in this project involved with Main contractor's payment application preparation and certifying after convincing the client,









.jpeg)
Title: Individual Residence at Nawala
Status: Completed (Defect liability period is going on)
Completed: 2022
Contract Amount: 20Mn
Project Nature: Individual residence & lump sum project.
QS4U Involvement: Construction was started in early 2019 and COVID lockdowns were affected to the project progress. Economic crisis was also affected to this lump sum project.






Title: Individual Residence at Malabe
Status: Completed (Defect liability period is going on)
Completed: 2022
Contract Amount: 80Mn
Project Nature: Individual residence & lump sum project.
QS4U Involvement: Construction was started in early 2020 and COVID lockdowns were affected to the project progress. Economic crisis was also affected to this lump sum project. Both parties mutually agreed to end the Contract agreement and QS4U implemented a new tool and both parties agreed to continue the project using stage wise quotations. Commencement of each stage material advance was to be paid and QS4U had to always make sure the client's money assurance since there wasn't any advance guarantee & the project cashflow.
.jpeg)
Title: Individual Residence at Pepiliyana
Status: Completed (Defect liability period is going on)
Completed: 2018
Contract Amount: 20Mn
Project Nature: Individual residence & constructed by various labour contractors
QS4U Involvement: Construction was started in early 2020 and COVID lockdowns were affected to the project progress. Economic crisis was also affected to this lump sum project. Both parties mutually agreed to end the Contract agreement and QS4U implemented a new tool and both parties agreed to continue the project using stage wise quotations. Commencement of each stage material advance was to be paid and QS4U had to always make sure the client's money assurance since there wasn't any advance guarantee & the project cashflow.
.jpeg)


.jpeg)

Title: Villa & Chalets at Ella
Status: Phase 01 Completed
Completed: 2022
Contract Amount: 05Mn
Project Nature: Constructed by various labour contractors.
QS4U Involvement: Construction was started in early 2019 and COVID lockdowns were affected to the project progress. Economic crisis was also affected to this lump sum project.
classified images included-








Title: Temple at Homagama - Charity Project
Status: Phase 01 Completed
Completed: 2022
Contract Amount: 05Mn
Project Nature: Constructed by various labour contractors.
QS4U Involvement: Construction was started in early 2019 and COVID lockdowns & economic crisis were affected to the project. QS4U was invited to prepare estimates & material and labour list for fund raising purposes.






Title: Independent Estimation for Police - Mt.Lavinia
Status: Dispute Resolved
Completed: 2020
Contract Amount: 01Mn
Project Nature: Constructed by various labour contractors.
QS4U Involvement: Construction was started in early 2019 and with the COVID lockdowns & economic crisis contractor left the project after getting more than eligible advances .