Project conducted on behalf of Engineers
All below mentioned project's Quantity Surveying part was conducted by QS4U crew on behalf of engineering organizations. With the performed capabilities and professionalism QS4U is still being hired by the engineering firms where the founder of QS4U was employed.
Design & Build project for PrintCare
Status: Completed Completed: 2020 Contract Amount: 24Mn Project Nature: QS4U Involvement:
![]() | ![]() | ![]() | ![]() |
|---|
LECO Customer Care Center at Nugegoda
-
Status: Tender
-
Completed: N/A
-
Contract Amount: 80Mn
-
Project Nature: In order to initiate to select a suitable contractor for the project, a public open tender notice was published.
-
QS4U Involvement: QS4U was appointed as the Engineer's quantity surveyor and project estimation & all the tender documents were prepared by QS4U. Project estimation was changed Due to economic crisis & the material inflation all bidders refused to continue the 03 times as design was changed one time, with the material price increases it was decided to allow CIDA price escalation and even with the price escalations project estimation had to be revised.
![]() | ![]() | ![]() | ![]() |
|---|
LECO Customer Care Center at Ambalangoda
Status: Completed
Completed: 2019
Contract Amount: 32Mn
Project Nature: Construction of Leco CCC was an open public tender and a measure & pay project.
QS4U Involvement: QS4U was assigned to the project at the middle of the project on behalf of the engineering firm.

LECO Customer Care Center at Ja-Ela
Status: Completed
Completed: 2019
Contract Amount: 34Mn
Project Nature: Construction of Leco CCC was an open public tender and a measure & pay project.
QS4U Involvement: QS4U was assigned to the project at the middle of the project on behalf of the engineering firm.
![]() | ![]() |
|---|---|
![]() | ![]() |
LECO Customer Care Center at Kandana
Status: Completed
Completed: 2020
Contract Amount: 59Mn
Project Nature: Construction of Leco CCC was an open public tender and a measure & pay project.
QS4U Involvement: QS4U was assigned to the project at the middle of the project on behalf of the engineering firm.
![]() |
|---|
LECO Customer Care Center at Payagala
Status: Completed
Completed: 2020
Contract Amount: 45Mn
Project Nature: Construction of Leco CCC was an open public tender and a measure & pay project.
QS4U Involvement: QS4U was assigned to the project at the middle of the project on behalf of the engineering firm.
![]() | ![]() | ![]() |
|---|---|---|
![]() | ![]() |
LECO Customer Care Center at Panadura
Status: Completed
Completed: 2020
Contract Amount: 33Mn
Project Nature: Construction of Leco CCC was an open public tender and a measure & pay project.
QS4U Involvement: QS4U was assigned to the project at the middle of the project on behalf of the engineering firm.
Namalgama Charity Project
Status: Completed
Completed: N/A
Contract Amount: 1Mn
Project Nature: Charity Project.
QS4U Involvement: Estimation was prepared.
![]() | ![]() | ![]() |
|---|
Other than these remarkable projects, QS4U has involved with several other projects several engineering firms in the island.
-
Serandib Engineering,
-
TNN Associates (Pvt) Ltd,
-
Tikiri Bibile Associates,
-
Ayahc Designs
.
-
DC Homes,
-
Ceylon Arch,
-
BIM Team,
-
YOMAX Engineering Solutions (Pvt) Ltd.
.